![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8569.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8567.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8544.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8545.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8554.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8559.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8548.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8546.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8569-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8567-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8544-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8545-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8554-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8559-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8548-315x210.jpg)
![](https://www.ichiba-k.com/wp_ik/wp-content/uploads/2023/12/IMG_8546-315x210.jpg)
着工から完成まで
2024.03.02
現場だより内装工事
断熱材の様子です。
現場発泡ウレタンフォーム、フォームライトSLを使用しています。
壁面で9cm、屋根下で18.5cm以上吹き付けています。
液状の状態から、現場で膨らんでいくので、すき間などにもしっかり入り込んで、気密性も高くなります。
そのあと、内装下地の石膏ボードを貼ります。
省令準耐火の基準で、外壁、間仕切りなどの壁の石膏ボードを、梁まで張り上げています。
見えなくなる部分ですが、今までの家とは違う部分です。
2024.02.14
現場だより外部工事
外壁の下地に、透湿防水シートを貼り、開口部回りは防水テープを貼って、しっかりと防水処理を行います。
外壁は、リシン吹付で仕上ますので、下地のボードを貼っていきます。
屋根は、和風の粘土瓦です。
2024.02.12
現場だより上棟
上棟、棟上げです。
工場でプレカットした木材を、現場で組み立てます。
多くの大工さんと、クレーンで組み立てていきます。
今回は、和風のお住まいです。
入母屋造りで、屋根の組み方が少し複雑になります。